The Tower Bridge Built in 1935
INTERESTING FACTS
Final Construction Cost $994,000
Electrical Installation Cost $100,000
Total Lenght 737’
Roadway width 52’
Center lift span is 209’ long
Weight of Center Span, Cables, & Counterweights 5,000,000 lbs
Lift span height above high water 100’
Tower Height 160’ tall
Two Towers rest on two concrete cylindars built to a depth of 50 feet below water
More than 5,000 cubic yards of concrete was used
6,500,000 pounds of steel was use in the frame work